Estimate costs
This feature may not be supported for every Fiery server.
- Select a processed job in the Job List. If the job is not processed, right-click it and select Process and Hold. For the estimate to be correct, you must use the same job property settings that will be used when the job is printed.
- Right-click the job and choose Estimate Ink, or select the job and choose Actions > Estimate Ink. While a job is being estimated, a progress bar shows the progress of the estimate next to the job title in the Held list.
- To cancel an estimate in progress, right-click the job and choose Cancel cost estimation, or click the X in the progress bar.
-
To view the completed estimate, do one of the following:
- View the Estimated Ink column in the job list.
- Click the Details link at the bottom of the Job Summary pane.
- Right-click the job and select Ink Estimation Details.
- Select Actions > Ink Estimation Details.
- For completed, printed jobs, add the columns to the Job Log.
- To view completed estimates for all the jobs in the job list, select File > Export Current View, and save the file to your computer.