Fiery Command WorkStation

Fiery Command WorkStation

Hide or show navigationPrevious topicNext topicSharePrintPDF

Set cost and job columns

  1. Log in as Administrator or Operator.
  2. Select Server > Cost Estimation Settings The window shows all colorants that are supported by the Fiery server, not just those that are currently installed or configured on the connected printer.
  3. Choose a currency symbol.
  4. Click the Edit icon (pencil) next to a name and enter the cost. You must enter a value to receive a cost estimate. To obtain the latest cost, contact your vendor. To receive an estimate of specialty colorants, enter only the costs of the colorants for which you are paying separately. Any colorants that are already included, such as by a maintenance contract, can be entered as zero.
  5. Click OK.
  6. To add the Estimated Cost column to Job Center, right-click any column header in the Job List and select Estimated Cost.